RAI furnished and installed the complete electrical portion of the project, including: medium voltage power distribution system, lighting, power
distribution to all equipment, fire alarm systems, datacom systems and security.
RAI scope included, but was not limited to:
- Electrical permitting
- Furnish, install and test new medium voltage distribution equipment at Allison Substation.
- Furnish, install and test new medium voltage cable systems to all four new stations.
- Furnish, install and test new 13.2 KV to 480 volt substations at 46th Street, 52nd Street,
56th Street and 60th Street passenger stations (2 substations per station).
- Furnish, install and test new emergency generators at each station.
- Furnish and install all secondary power distribution at each station.
- Furnish, install, test and certify all fire alarm systems at each station.
- Furnish and install all lighting in the building and on the platforms at each station.
- Furnish and install all street lighting at each station.
- Furnish and install all datacom systems at each station.
- Install all emergency phone and CCTV systems for the elevators at each station.
- Furnish and install power systems to all elevators and escalators at each station.
- Install all electronic call boxes (ECB's) on the platforms at each station.
- Install all other electrical at each station, including: wash-down stations, security conduit and wiring, elevator recall, etc.