RAI Commissioned 2 Main 15kv Switchgears, 1 Emergency 15kv Switchgear, 6 15kv Substations, 1 Fire Pump Substation,
1 1250kw Generator and 1 2000kw Generator. We also tested various other transformers, panel boards and breakers thru-out
the complex. All commissioning needed to take place over a 4 day weekend before the first pre-season game at the park.
This project used over 25 men working 3 shifts a day in order to meet this deadline. After the commissioning and testing we
supplied the Phillies Engineering and Maintenance staff with detailed drawings with a step by step de-energization and shutdown
procedure manual.